Q1)-To complete a work A and B takes 8 days, B and C takes 12 days, A,B and C takes 6 days. How much time A and C will take
24 days
16 days
12 days
8 days
Ans.- D


Q2)-Rahul and Sham together can complete a task in 35 days, but Rahul alone can complete same work in 60 days. Calculate in how many days Sham can complete this work ?
84 days
82 days
76 days
68 days
Ans.- A


Q3)-A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
20 days
22.5 days
25 days
30 days
Ans.- B


Q4)-A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?
11 days
13 days
15 days
17 days
Ans.- B


Q5)-P and Q need 8 days to complete a work. Q and R need 12 days to complete the same work. But P, Q and R together can finish it in 6 days. How many days will be needed if P and R together do it?
3
8
12
4
Ans.- B


Q6)-Ravi and Kumar are working on an assignment. Ravi takes 6 hours to type 32 pages on a computer, while Kumar takes 5 hours to type 40 pages. How much time will they take, working together on two different computers to type an assignment of 110 pages?
7 hours 30 minutes
8 hours
8 hours 15 minutes
8 hours 25 minutes
Ans.- C


Q7)-P,Q and R together earn Rs.1620 in 9 days. P and R can earn Rs.600 in 5 days. Q and R in 7 days can earn Rs.910. How much amount does R can earn per day?
Rs.40
Rs.70
Rs.90
Rs.100
Ans.- B


Q8)-Ram completes 60% of a task in 15 days and then takes the help of Rahim and Rachel. Rahim is 50% as efficient as Ram is and Rachel is 50% as efficient as Rahim is. In how many more days will they complete the work?
13 (1/3)
8(1/3)
5(5/7)
7(5/7)
Ans.- C


Q9)-Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:
15
16
18
25
Ans.- B


Q10)-A is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes. B alone can do the whole work in
15 days
10 days
9 days
18 days
Ans.- A